Data Centers in Germany: Current Market Developments (Update 2025) (Bitkom)
SaveSummary
- In 2025 installed capacity of all data centers and smaller IT installations in Germany grows by around 250 MW to 2,980 MW, a growth of 9%.p.5
- Colocation data centers exceed 50% of total capacity for the first time in 2025, with capacity growth of 17.5% in this segment.p.5
- Cloud capacity rises by 16.5% to 1,450 MW, so that 49% of German data center capacity is cloud infrastructure.p.5
- Data centers in Germany have an energy demand of 21.3 billion kWh in 2025.p.5
- Capacity in the four large US markets rose 43% in the first quarter of 2025, while the FLAP markets in Europe grew by an average of 7.2%.p.7
- Data center capacity in Germany is expected to reach around 5,000 MW in 2030.p.20
- The share of HPC and AI in data center capacity is 15% and is expected to rise to 40% by 2030.p.22
Key insights
- Frankfurt capacity grew 13.7%, the fastest of the four FLAP markets, with an expected additional supply of 187 MW.p.7
- CBRE puts the vacancy rate in Frankfurt/Rhine-Main at 3%, and Berlin at 1.7%.p.9
- The largest data center project, with 480 MW of IT connected load, is planned in Nierstein.p.11
- Small IT installations below 100 kW still make up 27% of capacity.p.11
- The average PUE improved to 1.43 in 2025 from 1.46 in 2024.p.12
- Hesse with the Frankfurt area has over 1,100 MW, more than one third of all capacity in Germany.p.15
- Deloitte forecasts that demand for AI data center capacity could triple from 1.6 GW to 4.8 GW between 2025 and 2030.p.22
- The largest known commercial AI data center in Germany, operated by Aleph Alpha, has 512 GPUs, while JUPITER at Forschungszentrum Jülich will have around 24,000 GPUs.p.23